Page 18 - HUB-4 Magazine Issue 100
P. 18

Material Recycling Facilities
Residual waste: engineering
the UK’s next resource
opportunity
As England implements major collection reforms and works towards a
statutory residual-waste target, general waste can no longer be treated
simply as the end of the line. Dr Benjamin Eule, Director at STADLER UK and
Head of Commissioning, explains why advanced sorting can provide a vital
second line of resource recovery.
Closing the recovery gap
For decades, residual waste was largely
viewed as the fraction remaining after
households and businesses had separated
recyclables. It was sent primarily to
landfill, mechanical biological treatment
or energy-from-waste, with sorting
focused on removing metals, producing
refuse-derived fuel or reducing disposal
volumes.
That model is changing. Even well-
established collection systems miss
recyclable plastics, ferrous and non-
ferrous metals and other recoverable
materials. With recycling rates under
pressure and growing demand for
secondary raw materials, allowing these
resources to pass directly to combustion
or landfill represents an increasingly
costly loss.
In England, policy reinforces the need to act. Residual waste,
excluding major mineral waste, must fall to no more than 287
kg per person by the end of 2042 – roughly 50% below 2019
levels. Simpler Recycling, Extended Producer Responsibility
and the Deposit Return Scheme will reshape collections and
material flows, but they will not eliminate the residual stream.
“Residual waste sorting should complement, not replace,
effective source separation,” says Eule. “Strong collection
systems need an effective final recovery stage, because even
the best separate collections will not capture everything.”
The greatest opportunity lies at high-volume points before
residual material enters energy-from-waste or landfill.
Recovering plastics and metals at this stage conserves
resources and can reduce the fossil carbon sent for
combustion. Although the Government confirmed in August
2026 that waste incineration will not enter the UK Emissions
Trading Scheme in 2028 as planned, a revised timetable and
final policy design will follow. Carbon exposure therefore
remains an important long-term planning consideration.
Engineering the complete process
Residual waste is one of the most demanding material
streams to process. Its composition varies by authority,
collection system and season, while contamination, batteries
and unpredictable items create operational and fire risks.
Recovering value reliably requires more than installing
individual sorting machines.
“Detecting a recyclable item is not the same as recovering a
marketable product,” Eule explains. “The complete process
must prepare and separate the material, deliver effective
quality control and maintain throughput, availability and safe
access for operation and maintenance. The business case
depends on the performance of the entire system – not one
individual machine.”
This complete-system approach is central to STADLER’s work.
The company supports authorities and operators from material
analysis and feasibility assessment through process design,
installation and commissioning to long-term optimisation. Its
engineers combine screening, ballistic and air separation,
magnets, eddy-current separators and optical sorting in
processes tailored to the input material and the intended
outlets for each recovered product. Adaptable layouts and
provision for future equipment allow plants to respond to
changing inputs, legislation and markets.
The Resursutvinning Stockholm facility demonstrates this
capability in practice. Designed and built by STADLER for
Stockholm Vatten och Avfall, its two independent lines process
up to 50 tonnes per hour and recover separately bagged
organic waste, plastics, ferrous metals and non-ferrous metals.
Automated control and flexible plant design enable
continuous optimisation as operating conditions change.
For UK authorities and operators, prevention, reuse and source
separation must come first, but valuable material will still
escape. STADLER brings international experience in designing
and delivering turnkey sorting plants together with the local
market knowledge of its UK team to help operators recover
value from this challenging stream. As Eule concludes: “What
we do not recover today becomes tomorrow’s disposal cost,
carbon liability and lost resource.”
| p18 |
www.hub-4.com Sept/Oct - Issue 100