- ShowplaceShowplace
Showplace, established in 1987, is a leading European provider of hospitality, exhibition and event management services. Based in Stratford upon Avon,...

New incinerator ash conditioning plant for The Waste Recycling Group.
New incinerator ash conditioning plant for The Waste Recycling Group.

- 1st November 2006
- Materials Handling
Portasilo has successfully completed a major contract for incinerator ash conditioning plant for The Waste Recycling Group (WRG), despite a very tight programme.
Sited at WRG`s waste disposal site at Norwood on the Isle of Sheppey, the plant receives incinerator ash from a new Energy from Waste Plant constructed for Kent Enviropower at Allington near Maidstone.
Severe planning constraints limited the height of the plant to 6.5 metres. Portasilo`s plant, conceived and developed jointly by Portasilo, WRG and WRG`s consultants, McLellan & Partners, was designed to fit within this limitation.
Two 86 cubic metre working capacity silos receive deliveries from bulk tankers. The silos are to Portasilo’s horizontal silo design. Each is mounted on load cells for accurate inventory control and to ensure adequate spare capacity to receive a full tanker load. The latest Portasilo silo safety systems minimises risk of over filling or over pressurising and resultant dust emissions.
Two independent streams were installed each incorporates a silo with its own discharge and transfer system, with screw conveyors transferring the ash to one of the ash conditioners. Each of these has twin shafts with paddles to ensure a homogeneous, conditioned, dust free material with a minimum of excess moisture.
These systems have been designed to gravity discharge directly into articulated dump truck with 11te load of conditioned ash within 12 minutes, inclusive of start up and run down time to clear the conditioner.
The conditioning and articulated dump truck loading facility is entirely contained within a steel framed, clad building within this height limitation.
Portasilo provided a complete turnkey installation, which includes silos, screw conveyors, ash conditioners, water tanks and the steel framed; clad building with all necessary access platforms and stairways.
All site services were supplied by Portasilo including compressed air system, water pumps and piping, site wiring, and a full control package.
Paul Scott
Portasilo Ltd
New Lane
Huntington
York
Yorkshire
YO32 9PR
T: 01904 624 872
Associated Links
Other news articles from Portasilo Ltd
Portasilo technical expertise delivers safe, efficient ferrous sulphate storage and precision-dosing system for Quinn Cement – right, first time
Portasilo Bulk Handling Systems provide bespoke solution for South West Water
Biomass handling demands a tailored technical solution
In just five weeks, Portasilo Bulk Handling Systems redesigned,
Portasilo Mild Steel Pressure Relief Valve
New Storage Silos for Nestle Purina.
Lafarge award contract to Portasilo at their Westbury site.
Lime Storage expanded at Buxton Lime - Tunstead Quarry.
New Extended Lime Storage Facilities at Buxton Lime Industries.
New Storage and Handling System for Castle Cement - Ribblesdale





